11th Street Local Bridge Lane Reductions To Occur December 26 Through January 14
Local Bridge Scheduled to be Completed Spring 2013
The District Department of Transportation (DDOT) will reduce the 11
th
Street local bridge to one inbound lane and one outbound lane on December 26, after the morning rush, to complete construction work on the bridge deck.
There are currently two inbound lanes and one outbound lane on the 11
th
Street local bridge. The lane reduction will remain in place through January 14, 2013 while crews complete the bridge deck construction. Once completed, the bridge will reopen to two lanes in each direction and include the new 16-feet pedestrian and bicycle path that connects to the Anacostia Riverwalk Trail.
For more information and to follow the bridge project and AWI Program’s progress, please visit the
11th Street Bridge project page
of AnacostiaWaterfront.org. To join the project or AWI community contact list or ask questions, please email
ddot.awi@dc.gov
or call
202-741-8528
.
To submit an article or to inquire about advertising send an email to
Advoc8te@congressheightsontherise.com.